A hotel furniture submittal register is a shared log that records which shop drawings, material samples and mock-ups have been submitted, who reviews each one, which revision they approved and what still needs a decision before production. Start with the item codes in the furniture schedule and give each drawing or sample its own entry.
In this worked example, a hotel is ordering 300 walnut bedside tables. The designer has signed off the dimensions. The owner still has to choose between two veneer samples. Which references should the buyer send to the factory?
A hotel furniture submittal register in practice
In this example from a furniture, fixtures and equipment (FF&E) package, two items generate four separate decisions. Each submission has its own reference so the reviewer can point to a specific drawing or physical sample.
| Submittal / item | Document or sample | Reviewer | Latest decision or action |
|---|---|---|---|
| SUB-001BST-01 bedside table | Shop drawing, Rev B | Interior designer | Approved15 Nov |
| SUB-002BST-01 bedside table | Walnut veneer WN-01, V2 | Owner’s representative | Approved18 Nov. Retain signed sample. |
| SUB-003SOF-01 lobby sofa | Upholstery fabric, V1 | Interior designer | ReviseSupplier to submit a closer color match. |
| SUB-004SOF-01 lobby sofa | Shop drawing, Rev B | Interior designer | Under reviewResponse due 20 Nov. |
The factory can identify the accepted bedside table finish by its sample reference, WN-01 V2. For the sofa, even a drawing approval on 20 November would leave the upholstery decision open.
What belongs in an FF&E submittal log?
You can build the register in a spreadsheet. Give each revision its own row, keep the submittal reference when a revision comes back, and use the reference and revision together to find a particular issue. These columns cover the decisions a buyer or manufacturer needs to trace.
| Field group | Suggested columns |
|---|---|
| Item | Submittal number, furniture item code, description, room or area, bill of quantities (BOQ) line. |
| Submission | Document or sample type, drawing number or sample ID, revision, file link or physical sample location. |
| Review | Submitted by, date submitted, responsible reviewer, response due date. |
| Decision | Status, dated reviewer comments, decision date, link to the written approval. |
| Follow-up | Next action, person responsible, resubmission date, revision replaced. |
| Production release | Release scope, approved drawing and sample references, person authorizing release, release date. |
For a package split between suppliers or production batches, add the supplier, purchase order and planned production date. Give the buyer a way to filter for overdue reviews and the factory a way to find the approved references for its batch.
Follow one item from BOQ to release
Carry the same item code from the bill of quantities through the specification, drawings, samples and production release. The BOQ gives the purchaser the quantity and scope. The register supplies the decision history for that line. For guidance on preparing those item references, see our hotel furniture BOQ guide.

| Record | What the buyer or factory should see |
|---|---|
| BOQ | BST-01, guestroom bedside table, 300 pieces. |
| Specification | BST-01, 600 × 450 × 550 mm, walnut veneer. |
| Shop drawing | BST-01, Rev B approved. Rev A retained and marked superseded. |
| Finish sample | BST-01, WN-01 V2 approved. The signed sample label matches the register. |
| Release record | Enter the quantity or batch authorized, Rev B, WN-01 V2 and the dated release decision. |
Three approvals to track separately
Shop drawing approval
The reviewer checks dimensions, construction, hardware and interfaces with the room. On a bedside table, that might mean checking drawer clearance against the bed and the position of a wall outlet. Record the drawing number and revision beside the decision. For a fuller drawing review, use our guide to production-ready furniture shop drawings.
Material and finish approval
Label the veneer, paint, metal, stone, fabric or leather sample with its reference and version. Record who accepted its color, texture or sheen and where the signed sample is held. The finish code alone can be ambiguous if the supplier submitted two versions under that code.
Sample and mock-up approval
A finished piece or mock-up room lets the team check things a drawing cannot settle, such as seat comfort, proportions and how adjacent finishes look together. Record the mock-up reference, the comments that apply to the full batch and who will check the changes. Use the hotel mock-up room acceptance form to document the sign-off.
How to read the approval status
Agree on the status names and who can issue each decision before the first submission. A designer’s “looks good” email is hard to act on if it omits the revision, the scope of approval or an open condition.
- Submitted / Under review
- The team has issued the file or sample. Move it to under review when the assigned reviewer starts checking it.
- Revise / Resubmitted
- Record what needs to change. When the supplier submits the revision, add its issue date and reference.
- Approved
- The authorized reviewer accepted the identified revision or sample for the stated scope.
- Approved with comments
- Record each condition, who will close it and which work the decision allows under the project’s approval procedure.
- Rejected
- Keep the decision and reason so the supplier knows what the replacement must address.
- Superseded
- A later issue has replaced this version. Keep the earlier file and its review history.
For revision control, record the latest submission and the revision released to the factory separately. If Rev C arrives after Rev B was released, flag the affected batch and ask the release authority whether work should continue. Receiving Rev C alone does not authorize the factory to build from it.
Build the review schedule
Work back from the date the factory needs an approved detail. Allow time for review, sample delivery and a revision where needed. For every open submission, name one person responsible for returning the decision. List the designer, operator, owner or procurement team members whose input that person needs.
| Submission | Planned issue | Decision due | Work that depends on it |
|---|---|---|---|
| SOF-01 shop drawing, Rev B | 18 Nov | 20 Nov | Confirm frame dimensions before cutting. |
| SOF-01 replacement fabric, V2 | 19 Nov | 24 Nov | Confirm the selected fabric before placing the bulk order. |
If the fabric sample misses its review date, the buyer can identify the affected order and contact the named reviewer. A package-wide figure such as “80% approved” would hide that dependency.
Before releasing furniture to production
Open the item record and match every required approval to the revision or sample the factory will use. For an upholstered chair, the release review might look like this.
| Requirement | Evidence to check |
|---|---|
| Dimensions and construction | The approved shop drawing identifies dimensions, hardware and interfaces. |
| Fabric and metal finish | The fabric and finish references match the signed samples held for production. |
| Foam and comfort | The foam specification matches the accepted chair sample where one is required. |
| Outstanding comments | Each comment has a recorded decision. The release identifies any work still on hold. |
| Release authority | The authorized person has recorded the date, batch, scope and references sent to the factory. |
If a finish is still pending, flag the operation it affects. Where the project permits a partial release, record exactly what the factory may start and which operations must wait. At ChiuChiu Furniture, drawings, material samples and production checks are part of the project workflow. Buyers can see how those stages fit together in our hotel furniture project support process.
Frequently asked questions
Who should approve hotel furniture shop drawings?
Use the approval authority named for the project. An interior designer may review design intent while the owner’s representative issues the final decision. Record who reviewed the drawing, who authorized it and the revision each decision covers.
How should we file an approval received by email?
Save or link the written decision in the register entry for that item and revision. Record the reviewer, decision date, scope and any conditions. If the message omits the revision or sample reference, ask the reviewer to identify it before marking the entry approved.
What happens if the same furniture item has two finishes?
Give each finish its own sample reference and record the rooms or quantities that use it. Before releasing either batch, match its BOQ line and drawing to the correct finish sample. That lets the factory distinguish two visually similar items carrying the same base code.